Frogmore Fullround System - Factory Acceptance and Test

The Frogmore Fullround System successfully passed the tests on the 3rd September.
Frogmore Connection tunnel is part of the Tideway project.


It was installed a mock-up with jobsite segments in order to carry out a full scale trial an simulate a complete cycle.


Site program required a high production rate for the two tunnels, 500m and 600m long.
The No.4 fullround shutters are designed to work with the hit / miss methodology.

Given the tight tolerances and the small dimension of the tunnel, the Engineering invested a huge amount of hours to develop a bespoke and innovative solution to comply with the requirements.


A complete process simulation and risk assessment have been part of the complex development.



Privacy
We use cookies to improve your browsing experience, analyze traffic, and optimize site performance.
You can accept all cookies, reject non-essential ones, or manage your preferences at any time.
Essential cookies are always active, while analytics and marketing cookies are used only with your consent.
All data is processed in accordance with the EU General Data Protection Regulation (GDPR).

Confirm
Reject